MASTER PLAN ROADS:

SL.NO. Name of the work Estimate Cost Rs. Crores Present status Probable Date of completion

 

MASTER PLAN ROADS:

 

 

1

100’-0” wide approach road to   Madhurawada IT SEZ.  - 0.9Km.

1.68

Work completed
recently

 

2

100’-0” wide road from Boyapalem Jn., on NH-5 to Kapulauppada Village – 3.2 Km

2.10

Work Completed
recently

 

3

80’-0” wide road connecting Boyapalem 100’-0’ road and Kapulauppada – VUDA layout   - 0.80 Km

1.57

80% of the work completed
balance held up for want of
finalization of alignment.

31-08-2011

4

80’-0” wide road connecting P.M.Palem and NH-5 near Car shed junction at  Madhurawada  - 1.80 Km

3.60

Work commenced and held up for want of shifting of water supply and power lines by GVMC and APEPDCL.  At present shifting work in progress.

30-09-2011

5

80'-0" wide road   from Navodaya School Jn. to Devimetta Hill at Kommadi   - 1.70 Km

4.49

25% of the work completed and work is in progress

30-09-2011

6

100’-0” wide road connecting NH-5 at  Marikavalasa jn.  and Harita Housing project junction – 3.2 Km. 

9.10

25% of the work completed and work is in progress

30-09-2011

7

100'-0" wide road connecting NH-5 at Yendada and Rushikonda VUDA Layout via Law College

9.10

25% of the work completed and work is in progress

30-09-2011

Vizag - Bheemili Beach Road

Project stretch - 25.50 Kms.
Project Cost - 60 Cr.
Funding - VUDA, R & B @ 50:50
4 lane road with median,
footpaths & electrification

0 - 2 Kms developed by VUDA initially.
Development of 6 - 15 Kms stretch
is under progress.
Design features include eco-friendly
in nature & Tourism concepts.

 

Widening & improvement of Master Plan roads

Roads completed

Rs. In Crs.

R3-100' wide road connecting Beach Road & NH-5 via Vignan School - 7.2 Kms.

25.45

R2-100' wide road connecting Marikavalasa Road connecting NH-5 to Beach Road - 3.3 Kms

11.80

R7-80' wide road connecting NH-5 via Law College to Mithilapuri Road- 3.0 Kms.

11.00

Demarcation Completed

Rs. In Crs.

R4 - 60' wide ghat road on Kailasa Hill (Strengthening & Improvement) - 2.0 Kms

4.60

R8 - 100' wide road connecting Beach Road & NH-5 via Kapuluppada & Boyyapalem - 6.0 Kms

21.25

R10 - 80' wide road connecting Dorathota road Via Vellanki to NH-5 - 2.00 Kms

7.00

R11 - 80' wide road connecting Duvvada Station via Narava to Gopalapatnam - 10.0 Kms.

35.15

R12 - 100' wide road connecting Bheemili to NH-5 via Rajula Tallavalasa - 5.0 Kms.

18.90

R14 - 80' wide road connecting Nidigattu to Nerallavalasa - 3.5 Kms

23.50

R15 - 80' wide road connecting Sontyam Padmanabham - 10.0 Kms.

11.50

R15 - 80' wide road connecting Sontyam Padmanabham - 10.0 Kms.

33.35

Road works under progress

Rs. In Crs.

R1-100' road connecting Appughar, Visakhapatnam to Bheemili Municipal Office Jn., Beach Road. - 24.0 Kms.

100

R6-80' wide road connecting Yendada 'Y' Junction to Rushikonda Layout Road - 2.5 Kms.

8.60

R7-80' wide road connecting NH-5 via Law College to Mithilapuri Road- 3.0 Kms.

9.50

R9-100' wide road connecting NH-5 Madhurawada to Bakkannaplem via S.No.56 - 2.0 Kms

7.85

R19-100' wide road connecting Duvvada to Aganampudi - 4.0 Kms.

14.95

Demarcation Completed

Rs. In Crs.

R16 - 80' wide road connecting Parawada to Anakapalli - 12.0 Kms.

38.35

R17 - 60' wide road connecting Pulagalapalem to Gurrampalem - 4.0 Kms.

12.30

R18 - 100' wide road connecting Duvvada to Sabbavaram via Asakapalli Jn. (Lankalapalem Road) - 11.0 Kms.

40.65

R20 - 100' wide road connecting Lankalepalem to Sabbavaram - 9.0 Kms.

32.55

 

Housing Projects

Yendada & Madhurwada

PPP Model
Total extent of Site : Ac. 80.00
Estimated Cost : Rs.581.20 Crores.
Work Entrusted to M/s. Jurong & ABS Infrastructure (India) Pvt., Ltd., Bangalore.
4235 units and provides Housing for 25,000 population
72 Lakhs Sft built up area
Villas, HIG, MIG, LIG & Flats
- School
- Poly Clinic
- Convenient Shopping
- Community Hall / Club House
Ground work to be started.

Vepagunta Housing

PPP Model
Total extent of Site : Ac. 55.00
Estimated Cost : Rs.226.50 Crores.
Work Entrusted to M/s. L&T and Vision Ventures Pvt., Ltd.,Hyderabad
689 units and provides Housing for 3500 population
15.50 Lakhs Sft built up are
- Villas, Flats - School
- Poly Clinic
- Convenient Shopping
- Community Hall/ Club House

Row Housing Project

Rushikonda Layout, Madhurwada, Visakhapatnam
Total extent of Site : Ac. 6.78Cts.


88 units and provides Housing
for 500 population Row-Housing of East & West facing buildings - Duplex type
- Crèche - Central park
- Convenient Shopping
- Community Hall/ Club House
50% work Completed

Housing Project

(Design, Build & Contract Model) Madhurwada, Visakhapatnam
Total extent of Site : Ac. 40.00Cts.
Project Cost : Rs.265.77cr

2024 units and provides Housing for 10,000 population
Group-housing of HIG & MIG
High-rise residential apartment buildings of 11 floors
School, Poly Clinic, Convenient Shopping,
Community Hall/ Club House
Work to be grounded.


Gandhi Place, Siripuram

BOT Basis
Total extent of Site : 6540 Sq.Yds
Estimated Cost : Rs.21.00 Crores.
Work Entrusted to M/s. Vaibhav Empire Pvt Ltd.,


A Huge commercial space with Sub cellar, Cellar, G+8 Floors 142500 Sft built up area
Parking, Retail Shopping, Food courts & Restaurant,
IT Incubation space, Services
Apartments and Guest House.

Ground work to be started.

IT Layouts at Rushikonda

Total extent of Site : Ac. 141.52
(Hill No.-2 & 3)
Construction Work of IT
Total No. of Plots proposed for IT Agencies : 25 Nos.


Total Plots allotted : 19 Nos.
Building Plans Approved : 13 Nos.
Building Plans received for scrutiny : 01 Nos.
Buildings are in Progress.
Yet to submit building plans : 05 Nos.
Vacant Plots : 06 Nos.

Buildings are in progress.